Saanvi Dixit
posted on 11 MayHidden charges in Noida Extension projects: real talk
Been looking for 6 months now, Noida Extension builders like Godrej, ATS, Gaursons sab achhe lagte hain. But I'm worried about hidden charges. PLC, EDC, maintenance deposits – do these builders demand extra at possession? Also, post-booking customer support kaisa rehta hai? Do they even pick up the phone?
#hidden-charges#noida-extension#first-time-buyer#customer-support#possession-cost
Comments
Honestly, some smaller builders are worse. At least with Godrej or ATS, the project quality is usually good, even if they hit you with some extra charges. My worry is more about structural issues post-possession, especially with the monsoon approaching. Any thoughts on that?
I think it really depends on the specific project and the builder's reputation at that time. Some Godrej projects in Noida Extension have had good reviews for quality and timely delivery, while others faced delays. The current market conditions are also pushing builders to finish projects faster, but sometimes quality suffers. It's a tough call for first-time buyers, you have to weigh everything carefully. Always check RERA filings for project status, not just marketing brochures.
Leakage is a big problem yaar. Especially in Noida flats.
That's a valid point about quality. But what's the use of good quality if you're constantly fighting for basic repairs? My friend's ATS flat had leakage issues within months, and customer service was a joke. They just kept passing the buck.
I booked a flat in a project near Alpha I, Greater Noida a couple of years back. The builder (not naming names but rhymes with 'Supremacy') initially quoted one price, but then at possession, they added 'development charges' and 'IFMS' (Interest-Free Maintenance Security) that collectively bumped up the cost by almost 7 lakhs! My budget went haywire. Customer support was non-existent after the booking amount was paid. Sirf naye customers ke liye phone uthate hain.
The RERA agreement was vague, it just mentioned 'other charges as applicable'. The builder exploited that loophole. My RERA possession date was Dec 2022, but I finally got possession in April 2024. Almost 1.5 years delay! They just keep extending deadlines. The penalty for delay was peanuts compared to the EMI burden.
Oh no, that's terrible! Did you check if those charges were mentioned in the RERA agreement or the initial booking form? What was your RERA possession date vs actual?
7 lakhs! That's insane! Same happened to my cousin in Ajayabpur.
Haan bhai, hidden charges are a nightmare. RERA ka bhi koi fayda nahi hota sometimes.
Absolutely! This is my biggest fear too. My friend bought in Alistonia Estate and got hit with a huge 'club membership' charge at possession that wasn't clearly mentioned earlier. Builders toh bas booking tak मीठा बोलते हैं.
Been looking for 6 months now, Noida Extension builders like Godrej, ATS, Gaursons sab achhe lagte hain. But I'm worried about hidden charges. PLC, EDC, maintenance deposits – do these builders demand extra at possession? Also, post-booking customer support kaisa rehta hai? Do they even pick up the phone?