posted on 13 MayHyderabad investors, Sattva Lake Ridge delivery pe kya thoughts hain?
My recent portfolio review shows Sattva Lake Ridge's possession dates slipping. Builder ka track record pehle bhi concern tha. Is anyone else worried about ROI due to these delays? Kya ground reality hai?
#sattva-lake-ridge#project-delivery#hyderabad-real-estate#investor#possession-delay
Comments
So, basically, avoid Sattva Lake Ridge for now, ya negotiate hard on penalty clauses? What's the general consensus?
Toh phir kya karein? Is there any other reliable project in that price range near Gachibowli or Kokapet that we should look into? Or is it better to wait for a bit?
Exactly. The market is definitely up, so prices won't dip. But if you're a first-time buyer, focus on builders with a proven track record of timely delivery, even if the per sqft rate is slightly higher. The financial stress of paying rent + EMI while waiting for a delayed possession is immense. I'd say, do your due diligence on the builder's past 3-4 projects, not just their current promises. Lake Ridge has 897 units, a massive project, so any delay will impact hundreds.
Waiting is always an option, but prices won't come down much in Hyderabad. Instead of Lake Ridge, check out projects with a better completion record, even if they are slightly outside your preferred area. Sometimes, paying a little extra for peace of mind is worth it.
Hyderabad real estate is hot right now, but delays like these can really kill your investment. Especially for first-time buyers.
Sahi keh rahe ho sab. But official RERA status kya bolta hai? Kya unhone formally date change ki hai ya abhi bhi wohi purani date dikha raha hai? I checked the RERA site, and it still shows 'upcoming' project status, which is strange for something that should be well into construction if it's for 2028 delivery.
It's a common tactic, unfortunately. My cousin booked in Ameerpet and faced similar issues with a different builder. They show 'upcoming' for ages, milk the pre-launch benefits, and then slowly push dates. With Hyderabad's current property boom, builders know people are desperate to invest, so they take advantage. The government needs stricter RERA enforcement for these 'upcoming' projects.
Official date toh bas dikhane ke liye hai. Inke previous projects mein bhi yahi hua hai. Never trust the first date they tell you.
Haan, RERA pe abhi bhi 2028-01-01 hi dikha raha hai for Sattva Lake Ridge. But that's the *official* date. Builders often keep that as a buffer. The initial promise was usually much earlier, maybe late 2026 or early 2027. That's where the 'slipping' part comes in.
Yaar, I saw that too! Sattva Lake Ridge ka mention sunte hi darr lagta hai. Builder ka track record on deliveries, especially post-pandemic, is seriously questionable. My agent even hinted ki 2028-01-01 bhi just a tentative date hai. ROI ka toh pata nahi, bas ghar mil jaaye time pe, wahi badi baat hai.
Bhai, mera Alwal mein ek project tha inka, 2 saal late kar diya. Har baar naya bahana. Lake Ridge mein 897 units hain, socha tha bada project hai toh shayad better management hoga, but lagta hai same story hai. My friend who booked there got a revised possession letter with the 2028 date, but earlier they were promising late 2026. This builder is notorious for over-committing and under-delivering. Be very careful with their 'upcoming' projects.
Totally agree! First-time buyer hoon, aur aise delays sunke toh BP high ho jaata hai. Budget tight hai, rent bhi dena hai, upar se EMI. Bahut tension ho rahi hai.