Rajvansh Shivoy Ghaziabad: Daily living has surprises.
₹37.5 lakh mein Shivoy ka 2BHK liya, March mein possession mila. Do mahine ho gaye hain. Clubhouse abhi fully functional nahi, kids play area chhota laga. Market aur school paas hain, that's good. Parking ka issue lag raha hai. Kya aap log ko bhi aisa laga? Overall, daily living experience kaisi hai?
Comments
Overall, daily living experience kaisi hai, yeh toh tab pata chalega jab sab amenities functional hon. Abhi toh sounds like a work in progress. ₹37-38 lakh for an ongoing project with these issues in Ghaziabad, seems a bit high. Current market conditions mein toh negotiation ki bhi gunjaish hoti hai. Kya kisi ne negotiation try kiya yahan pe?
Market aur school paas hain, that's a plus point, but the possession date discrepancy is a huge red flag. UPRERAPRJ854600 ke hisaab se toh 2025 end hai. If you're a first-time buyer like me, always double-check these things. Builders often show sample flats with great amenities but deliver much later or with compromises. Be careful.
₹37.5 lakh mein 2BHK, aur parking ka issue? Bhaisaab, Ghaziabad mein Abhay Khand mein bhi thode better options mil jaate hain is range mein. Total 114 units hain, agar har unit ko ek car bhi consider karein toh parking ki problem toh hogi hi. Builder ko yeh sochna chahiye tha. Kids play area chhota hai, yeh bhi big NO for families.
Parking aur clubhouse ka issue sunke darr lag raha hai. Builder Rajvansh ka reputation kaisa hai Ghaziabad mein? Main bhi Ahinsa Khand II mein rent pe rehta hoon aur property dekh raha. Yeh project ONGOING status mein hai, toh phir possession kaise mil gaya March mein? Koi batao please.
I agree with U8, RERA site pe toh 2025 hi dikha raha hai. Maybe the poster got a 'soft possession' or something? But that's not actual possession. Clubhouse aur kids play area ka issue toh common hai, builders delay karte hain amenities. Total 114 units hain, parking toh kam padega hi.
Rajvansh Shivoy ka RERA number UPRERAPRJ854600 hai. Isko check karo, wahan clearly likha hai possession date 2025-12-01. Ya toh original poster ne galat information di hai, ya phir woh koi aur phase ki baat kar raha hai. Builder ki website bhi check karni chahiye.
Rajvansh Shivoy ka post dekha. Original poster ko March mein possession mila hai, but Propmyna pe toh 2025 December dikha raha hai as per RERA. Yeh kya scene hai? Main bhi first-time buyer hoon, confusion ho rahi hai. Kahin yeh builder late toh nahi karta possession?
Possession date ka game pura chalta hai. Mere friend ne bhi ek project mein book kiya tha, bola tha 2023 end, ab 2025 tak khinch gaya. Is builder ka track record check karna padega before putting your money. Bahut risky hota hai yeh sab.
Haan bhai, mujhe bhi yahi laga! Builder ne koi early possession diya hoga ya phir poster ne galat likha. Thoda tension ho raha hai, maine bhi socha tha yahan dekhoon. Yeh discrepancy toh sahi nahi hai.